Template and law — no legal advice

Renovation contract annex template.
Extra work in writing.

Once the tiles are off, a corroded pipe shows up, and the client wants one more socket. An annex records what changes: the work, the price, the dates and payment. Below you will find a template and the rules worth knowing.

This is not legal advice. The template shows a typical annex layout. Adapt it to your contract and local jurisdiction, or ask a lawyer if in doubt.Law checked on 7 November 2026.

Template

Renovation contract
annex template.

Fill in the boxed fields with the details from your contract. The layout follows the annex Kaldrix creates from a quote.

Annex no. number

to contract no. contract number of contract date, concluded on annex date between contractor: company name, tax ID, address and client: full name, address

§ 1. Subject of the annex

  1. The Parties amend contract no. contract number concluded on contract date (the Contract).
  2. Reason for the change: e.g. replacing a corroded riser found after removing the tiles.
  3. The scope of work changes by the additional and omitted work listed in the table.
Changes to the scope of work
WorkTypeUnitQuantityUnit price netVAT
e.g. replacing a section of the water riseradditional worklin. mquantitypricerate
e.g. installing a bathomitted workpcsquantitypricerate

§ 2. Price

  1. The price increases / decreases by amount and currency gross (amount net + VAT amount).
  2. Price before the change: amount and currency gross. Price after the change: amount and currency gross.

§ 3. Dates

  1. The completion date changes from … to … / does not change.

§ 4. Payment

  1. The increase is payable e.g. as a separate instalment within 7 days of concluding the annex / together with the last instalment of the Contract.

§ 5. Final provisions

  1. All other provisions of the Contract remain unchanged.
  2. The annex is an integral part of the Contract and takes effect on the day it is concluded.
  3. The annex was made in the form required by the Contract, e.g. in two identical copies, one for each Party.
ContractorClient

An illustrative template. The parties to the contract agree the amounts, currency, dates and form of the annex under applicable local law.

Statutory reference

Civil-law reference
on changing a contract.

Reference rules from civil law (cited from the Polish Civil Code and EU/Polish consumer rules for contracts governed by Polish law — check local contract rules in your country).

  • Construction and renovation contracts

    A construction works contract should be confirmed in writing (art. 648 § 1 KC). The rules on this contract apply accordingly to a contract for the renovation of a building or structure (art. 658 KC). [1]

  • An annex in the same form

    Supplementing or changing a contract requires the form that the law or the parties set for concluding it (art. 77 § 1 KC). [1]

  • When the form is missing

    If the law does not make the form a condition of validity, a missing written form does not void the contract. In a dispute, however, evidence from witnesses or the parties’ own testimony that the contract was made is generally not admissible. There are exceptions, for example when both parties agree or a document makes the contract plausible (art. 73 § 1 and art. 74 KC). [1]

  • Written and documentary form

    Written form is met by a handwritten signature (art. 78 § 1 KC). A qualified electronic signature is equivalent to it (art. 78¹ KC). Documentary form is a declaration in a document that makes it possible to identify who made it (art. 77² KC). [1]

  • Additional work under a cost-estimate price

    If the client prepared the list of work, the contractor may demand a suitable price increase for necessary additional work. If the contractor prepared it, only when the work could not be foreseen despite due care. There is no increase for additional work done without the client’s consent (art. 630 KC). [1]

  • A significant price increase

    When the cost-estimate price must rise significantly, the client may withdraw from the contract without delay and pay a suitable part of the price (art. 631 KC). [1]

  • A lump-sum price

    With a lump sum, the contractor may not demand more even if the scope or costs could not be foreseen when the contract was made. If an unforeseeable change of circumstances means the work would cause the contractor a gross loss, a court may raise the lump sum or dissolve the contract (art. 632 KC). [1]

  • Contract-for-work rules and construction

    Articles 630–632 sit in the part on contracts for a specific work (umowa o dzieło). For construction contracts the Code refers to those rules only in some matters (art. 656 § 1 KC). Whether and how they apply to your contract comes from case law — a question for a lawyer. [1]

  • A client who is a consumer

    When a contract with a consumer is concluded away from the business premises, the consumer may withdraw within 14 days, or within 30 days after an unannounced visit by the business. For services, the period runs from the day the contract is concluded. [2]

In Kaldrix

An annex from your quote,
no retyping.

Kaldrix builds the annex from the items of the accepted quote and works out the difference. The client accepts or rejects it in the browser with an email code, without an account.

  1. Choose the items

    Change the quantity of a contract item, add a service from your price list or type in the work by hand.

  2. Check the amounts

    Kaldrix works out the net, VAT and gross change and the price after the annex.

  3. Send it to the client

    The client opens the annex and downloads the PDF. On acceptance we record the full name, date and time, IP address and a hash of the document.

  4. The plan follows the annex

    Once the annex is accepted, the contract price, instalments and dates change.

Sources

Where this comes from.

The text of the Act and an official page, in Polish. The law can change, so check the current version.

  1. Civil Code (Kodeks cywilny), consolidated text Dz.U. 2026 item 795, art. 73, 74, 77, 77², 78, 78¹, 630–632, 648, 656, 658 — Journal of Laws, api.sejm.gov.pl. Checked 7 November 2026.
  2. Prawo odstąpienia od umowy — terminy (Right of withdrawal — time limits) — UOKiK, prawakonsumenta.uokik.gov.pl. Checked 7 November 2026.

Questions

Renovation contract annex — questions

When do I need an annex?

When the parties change the contract, such as the scope of work, the price or the dates. The change requires the form that the law or the parties set for concluding the contract (art. 77 § 1 KC).

Does accepting with an email code replace a signature?

That is a legal question this page does not answer. On acceptance Kaldrix records the full name, date and time, IP address and a hash of the document. Written form is met by a handwritten signature or a qualified electronic signature (art. 78 and 78¹ KC).

What if I do extra work without the client’s consent?

The Code says a contractor may not demand a higher cost-estimate price for additional work done without the client’s consent (art. 630 § 2 KC).

Is this template free?

Yes. You can copy it and adapt it to your contract.

Make annexes from your quotes in Kaldrix.

A contractor account: quotes at your own rates, and the client accepts quotes and annexes with an email code.

Try it free for 14 days

Contractor account. 14 days on the Base plan, no card and no automatic charges. Application terms · Application privacy.