Renovation handover protocol template.
Sign off completed work clearly.

A handover protocol closes a work stage or the entire flat renovation: it confirms what was completed, lists any snagging items with a fix date and supports final invoicing. Copy the free template below.

This is not legal advice. The template illustrates a typical renovation handover record. Adapt it to your contract and local jurisdiction, or consult a lawyer.Statutory references checked on 7 November 2026.

Free template

Renovation handover
protocol template.

Fill in the boxed placeholders with details from your contract. Prepare two signed copies — one for the contractor and one for the client.

Interim / Final Work Handover Protocol No. number

drawn up on handover date at property address under Contract No. contract number dated contract date between Contractor: company name, tax ID, address and Client: full name, address

§ 1. Scope of Inspected Work

  1. Representatives present: for the Contractor full name and the Client full name, inspecting work carried out from start date to completion notice date.
  2. The inspection covers the scope under the Contract and Annex No. annex numbers, or write: none.
Inspected rooms or work stages
Room / stageCompleted work scopeInspection result
e.g. Bathroom 5.4 m²e.g. waterproofing, tiling, sanitarywareaccepted / accepted with snags
e.g. Living room & kitchen 24 m²e.g. skim coat, painting, flooring, skirtingaccepted / accepted with snags

§ 2. Quality Findings and Snagging List

  1. The Parties confirm that the work was completed in accordance with the Contract with no defects / with minor snagging items listed below.
  2. Snagging items to remedy: item description and room, or write: none found.
  3. Agreed deadline to remedy snagging items and re-inspect: date, or write: not applicable.

§ 3. Handed-Over Documents, Keys and Meter Readings

  1. The Contractor hands over to the Client: e.g. 2 key sets, pressure/electrical test records, product warranty cards.
  2. Meter readings at handover (if applicable): electricity kWh, cold water m³, hot water m³.

§ 4. Stage or Final Settlement

  1. This protocol forms the basis for settling the interim milestone / final balance under Clause clause number of the Contract in the gross amount of amount and currency.

§ 5. Final Provisions

  1. Additional remarks by either Party: remarks, or write: none.
  2. Prepared in two identical copies, one for each Party.
ContractorClient

Illustrative template. Handover rules, retention and payment triggers depend on your written contract and applicable law.

Statutory context

Key rules on work
handover and defects.

Reference rules under the Polish Civil Code (applied to contracts governed by Polish law).

  • Duty to hand over and accept completed work

    Under a construction or renovation contract governed by the Polish Civil Code, the contractor undertakes to hand over the agreed work and the client undertakes to accept it and pay the agreed price (Articles 647 and 658 KC). [1]

  • Interim stage handovers

    Unless the contract states otherwise, the client accepts completed stages progressively at the contractor’s request against the corresponding part of the remuneration (Article 654 KC). [1]

  • Concealed work before tiling or boarding

    Waterproofing membranes, concealed plumbing and electrical runs should be inspected and photographed before tiling or plastering closes them up. [1]

  • Defects and statutory warranty

    Rules on defective performance and statutory warranty for defects refer to work-contract and sale warranty provisions (Article 656 § 1 in conjunction with Articles 638, 556 and 568 KC). [1]

In Kaldrix

From quote and annex
to an organised handover.

When the accepted quote, extra-work annexes and site log live in one project, handover takes minutes instead of digging through old messages.

  1. Accepted quote & annexes

    Start from a clear room-by-room list of base work and email-approved annexes.

  2. Site log & concealed-work photos (Pro)

    Record daily progress and photos of waterproofing or wiring right inside the job.

  3. Crew tasks & snagging items (Pro)

    Assign any handover touch-ups to crew members with due dates.

  4. Documents & cost control together

    Keep the signed handover scan, quote PDFs and supplier invoices in one project folder.

Sources

Official legal source.

Consolidated statutory text in the Polish Journal of Laws. Verify current rules for your jurisdiction.

  1. Polish Civil Code (consolidated text, Journal of Laws 2026 item 795), Articles 556, 568, 638, 647, 654, 656, 658 — Journal of Laws, api.sejm.gov.pl. Checked on 7 November 2026.

Questions

Renovation handover protocol — FAQ

Why sign an interim handover during a renovation?

It confirms concealed stages (such as bathroom waterproofing, plumbing or wiring) before they are covered with tiles or plaster, and documents milestone payments.

What if minor touch-ups remain on handover day?

List each item clearly in § 2 with the room name, exact fix deadline and re-inspection date so both sides share one written list.

Should the handover protocol mention annexes?

Yes. Listing approved annexes in § 1 confirms that the inspection covers the updated scope and final contract total.

Is this template free to use?

Yes. Copy, print and adapt it freely to match your renovation contract.

Keep quotes, annexes and site records in one place.